Systemic risk assessment: a case study

Research output: Contribution to journalArticle

40 Citations (Scopus)

Abstract

Project Risk Registers have been used extensively for many years. However, they do not account for the interaction between risks, for example, the occurrence of one risk exacerbating other risks or portfolios of risks being more significant than the sum of the individual risks. This leads to the need to consider 'risk systemicity' as a part of risk analysis. This paper reports on a specific case for a large multinational project based organization, one that the authors had been involved with in the analysis of a number of projects that had massive cost overruns. Following these analyses the organization was persuaded of the importance of risk systemicity. The organization therefore engaged the authors to develop a 'Risk Filter'. This filter is a tool for identifying areas of risk exposure on future projects and creating a framework for their investigation. The 'Risk Filter' is now used on all projects ever since its introduction; by the end of May 2003 it had been used by nine divisions, on over 60 major projects, and completed by 450 respondents. It is also used at several stages during the life of a project to aid in the risk assessment and management of each project, and contributes to a project database.
LanguageEnglish
Pages39-51
Number of pages12
JournalJournal of the Operational Research Society
Volume58
Issue number1
DOIs
Publication statusPublished - 2007

Fingerprint

Risk assessment
Systemic risk
Risk analysis
Risk management
Filter

Keywords

  • causal mapping
  • project risk
  • risk management
  • management theory

Cite this

@article{9618e561240542b2ac01b0420faa0627,
title = "Systemic risk assessment: a case study",
abstract = "Project Risk Registers have been used extensively for many years. However, they do not account for the interaction between risks, for example, the occurrence of one risk exacerbating other risks or portfolios of risks being more significant than the sum of the individual risks. This leads to the need to consider 'risk systemicity' as a part of risk analysis. This paper reports on a specific case for a large multinational project based organization, one that the authors had been involved with in the analysis of a number of projects that had massive cost overruns. Following these analyses the organization was persuaded of the importance of risk systemicity. The organization therefore engaged the authors to develop a 'Risk Filter'. This filter is a tool for identifying areas of risk exposure on future projects and creating a framework for their investigation. The 'Risk Filter' is now used on all projects ever since its introduction; by the end of May 2003 it had been used by nine divisions, on over 60 major projects, and completed by 450 respondents. It is also used at several stages during the life of a project to aid in the risk assessment and management of each project, and contributes to a project database.",
keywords = "causal mapping, project risk, risk management, management theory",
author = "F. Ackermann and C. Eden and T.M. Williams and S.M. Howick",
year = "2007",
doi = "10.1057/palgrave.jors.2602105",
language = "English",
volume = "58",
pages = "39--51",
journal = "Journal of Operational Research Society",
issn = "0160-5682",
number = "1",

}

Systemic risk assessment : a case study. / Ackermann, F.; Eden, C.; Williams, T.M.; Howick, S.M.

In: Journal of the Operational Research Society, Vol. 58, No. 1, 2007, p. 39-51.

Research output: Contribution to journalArticle

TY - JOUR

T1 - Systemic risk assessment

T2 - Journal of Operational Research Society

AU - Ackermann, F.

AU - Eden, C.

AU - Williams, T.M.

AU - Howick, S.M.

PY - 2007

Y1 - 2007

N2 - Project Risk Registers have been used extensively for many years. However, they do not account for the interaction between risks, for example, the occurrence of one risk exacerbating other risks or portfolios of risks being more significant than the sum of the individual risks. This leads to the need to consider 'risk systemicity' as a part of risk analysis. This paper reports on a specific case for a large multinational project based organization, one that the authors had been involved with in the analysis of a number of projects that had massive cost overruns. Following these analyses the organization was persuaded of the importance of risk systemicity. The organization therefore engaged the authors to develop a 'Risk Filter'. This filter is a tool for identifying areas of risk exposure on future projects and creating a framework for their investigation. The 'Risk Filter' is now used on all projects ever since its introduction; by the end of May 2003 it had been used by nine divisions, on over 60 major projects, and completed by 450 respondents. It is also used at several stages during the life of a project to aid in the risk assessment and management of each project, and contributes to a project database.

AB - Project Risk Registers have been used extensively for many years. However, they do not account for the interaction between risks, for example, the occurrence of one risk exacerbating other risks or portfolios of risks being more significant than the sum of the individual risks. This leads to the need to consider 'risk systemicity' as a part of risk analysis. This paper reports on a specific case for a large multinational project based organization, one that the authors had been involved with in the analysis of a number of projects that had massive cost overruns. Following these analyses the organization was persuaded of the importance of risk systemicity. The organization therefore engaged the authors to develop a 'Risk Filter'. This filter is a tool for identifying areas of risk exposure on future projects and creating a framework for their investigation. The 'Risk Filter' is now used on all projects ever since its introduction; by the end of May 2003 it had been used by nine divisions, on over 60 major projects, and completed by 450 respondents. It is also used at several stages during the life of a project to aid in the risk assessment and management of each project, and contributes to a project database.

KW - causal mapping

KW - project risk

KW - risk management

KW - management theory

U2 - 10.1057/palgrave.jors.2602105

DO - 10.1057/palgrave.jors.2602105

M3 - Article

VL - 58

SP - 39

EP - 51

JO - Journal of Operational Research Society

JF - Journal of Operational Research Society

SN - 0160-5682

IS - 1

ER -