Remote controlled partial discharge acquisition unit

M.H. Foo, J.J. Soraghan, W.H. Siew, J.S. Pearson

Research output: Contribution to conferencePaper

102 Downloads (Pure)

Abstract

Online partial discharge (PD) analysis for underground high voltage cables has major advantages over the offline techniques. Online techniques usually involve PD data acquisition, storage and post-processing of the data. However, the data acquisition process can be time consuming and troublesome because of design procedures and protocols required before commencement of data acquisition. This paper presents a robust remote controlled partial discharge acquisition unit for underground high voltage cable networks. This system is uniquely designed to incorporate the difficulties of accessibility, especially for remotely located
substations. Real field data from a 33kV network is included in the paper.
Original languageEnglish
Number of pages4
Publication statusPublished - May 2003
Event17th International Conference on Electricity Distribution (CIRED 2003) - Barcelona, Spain
Duration: 12 May 200315 May 2003

Conference

Conference17th International Conference on Electricity Distribution (CIRED 2003)
Country/TerritorySpain
CityBarcelona
Period12/05/0315/05/03

Keywords

  • remote controlled
  • partial discharge
  • acquisition unit

Fingerprint

Dive into the research topics of 'Remote controlled partial discharge acquisition unit'. Together they form a unique fingerprint.

Cite this