Impact of C2C Operation on DG Capacity in HV Networks

Research output: Working paper

Abstract

The objective of the Capacity to Customers (C2C) project, an Ofgem Low Carbon Network Fund project led by Electricity North West Limited (ENWL) in conjunction with several industrial and academic partners, is to test a combination of new automation technology, non-conventional network operational practices (i.e., increased network interconnection), and commercial demand-side response (DSR) contracts. These changes will allow ENWL to increase demand and generation connections on a selection of trial circuits – representing approximately 10% of its high voltage (HV) system – without resorting to conventional reinforcement measures. The project will thereby “release” inherent spare capacity in the HV system in order to accommodate the future forecast increases in demand and DG, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement.
This paper documents work undertaken by the University of Strathclyde to quantify the ability of C2C network operation to accommodate additional DG capacity. This has been achieved using simulation models based upon actual system data from a representative proportion of the C2C trial circuits.
LanguageEnglish
PublisherUniversity of Strathclyde
Number of pages25
Publication statusPublished - Dec 2014

Fingerprint

Reinforcement
Electricity
Networks (circuits)
Electric potential
Environmental impact
Automation
Carbon
Costs

Keywords

  • capacity to customers
  • low carbon network
  • network operational practices
  • network interconnection
  • distributed generation

Cite this

@techreport{9c201290d99c47e59b12907cd9501ea4,
title = "Impact of C2C Operation on DG Capacity in HV Networks",
abstract = "The objective of the Capacity to Customers (C2C) project, an Ofgem Low Carbon Network Fund project led by Electricity North West Limited (ENWL) in conjunction with several industrial and academic partners, is to test a combination of new automation technology, non-conventional network operational practices (i.e., increased network interconnection), and commercial demand-side response (DSR) contracts. These changes will allow ENWL to increase demand and generation connections on a selection of trial circuits – representing approximately 10{\%} of its high voltage (HV) system – without resorting to conventional reinforcement measures. The project will thereby “release” inherent spare capacity in the HV system in order to accommodate the future forecast increases in demand and DG, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement.This paper documents work undertaken by the University of Strathclyde to quantify the ability of C2C network operation to accommodate additional DG capacity. This has been achieved using simulation models based upon actual system data from a representative proportion of the C2C trial circuits.",
keywords = "capacity to customers, low carbon network, network operational practices, network interconnection, distributed generation",
author = "Blair, {Steven Macpherson} and Campbell Booth",
year = "2014",
month = "12",
language = "English",
publisher = "University of Strathclyde",
type = "WorkingPaper",
institution = "University of Strathclyde",

}

Impact of C2C Operation on DG Capacity in HV Networks. / Blair, Steven Macpherson; Booth, Campbell.

University of Strathclyde, 2014.

Research output: Working paper

TY - UNPB

T1 - Impact of C2C Operation on DG Capacity in HV Networks

AU - Blair, Steven Macpherson

AU - Booth, Campbell

PY - 2014/12

Y1 - 2014/12

N2 - The objective of the Capacity to Customers (C2C) project, an Ofgem Low Carbon Network Fund project led by Electricity North West Limited (ENWL) in conjunction with several industrial and academic partners, is to test a combination of new automation technology, non-conventional network operational practices (i.e., increased network interconnection), and commercial demand-side response (DSR) contracts. These changes will allow ENWL to increase demand and generation connections on a selection of trial circuits – representing approximately 10% of its high voltage (HV) system – without resorting to conventional reinforcement measures. The project will thereby “release” inherent spare capacity in the HV system in order to accommodate the future forecast increases in demand and DG, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement.This paper documents work undertaken by the University of Strathclyde to quantify the ability of C2C network operation to accommodate additional DG capacity. This has been achieved using simulation models based upon actual system data from a representative proportion of the C2C trial circuits.

AB - The objective of the Capacity to Customers (C2C) project, an Ofgem Low Carbon Network Fund project led by Electricity North West Limited (ENWL) in conjunction with several industrial and academic partners, is to test a combination of new automation technology, non-conventional network operational practices (i.e., increased network interconnection), and commercial demand-side response (DSR) contracts. These changes will allow ENWL to increase demand and generation connections on a selection of trial circuits – representing approximately 10% of its high voltage (HV) system – without resorting to conventional reinforcement measures. The project will thereby “release” inherent spare capacity in the HV system in order to accommodate the future forecast increases in demand and DG, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement.This paper documents work undertaken by the University of Strathclyde to quantify the ability of C2C network operation to accommodate additional DG capacity. This has been achieved using simulation models based upon actual system data from a representative proportion of the C2C trial circuits.

KW - capacity to customers

KW - low carbon network

KW - network operational practices

KW - network interconnection

KW - distributed generation

M3 - Working paper

BT - Impact of C2C Operation on DG Capacity in HV Networks

PB - University of Strathclyde

ER -