Demonstration of adaptive overcurrent protection using IEC 61850 communications

Research output: Contribution to conferencePaper

4 Citations (Scopus)
315 Downloads (Pure)

Abstract

This paper contains a description of an adaptive protection
scheme that has been implemented and demonstrated in a
hardware in the loop simulation environment using
commercially available protection hardware and IEC
61850 communications.The implementation is based on an
actual 11kV system which includes distributed generation
and network automation.
IEC 61850 communications offers several benefits for the
implementation of adaptive protection, but also presents
some limitations which are discussed in the paper. An
alternative approach to overcome a number of the
limitations is also presented.
Original languageEnglish
Number of pages4
Publication statusPublished - 2013
EventCIRED 2013, 22nd International Conference on Electricity Distribution - Stockholm, Sweden
Duration: 10 Jun 201313 Jun 2013

Conference

ConferenceCIRED 2013, 22nd International Conference on Electricity Distribution
CountrySweden
CityStockholm
Period10/06/1313/06/13

Fingerprint

Overcurrent protection
Demonstrations
Communication
Distributed power generation
Automation
Hardware

Keywords

  • adaptive overcurrent protection
  • IEC 61850
  • communications

Cite this

Coffele, F., Blair, S. M., Booth, C., Kirkwood, J., & Fordyce, B. (2013). Demonstration of adaptive overcurrent protection using IEC 61850 communications. Paper presented at CIRED 2013, 22nd International Conference on Electricity Distribution, Stockholm, Sweden.
Coffele, Federico ; Blair, Steven Macpherson ; Booth, Campbell ; Kirkwood, John ; Fordyce, Bob. / Demonstration of adaptive overcurrent protection using IEC 61850 communications. Paper presented at CIRED 2013, 22nd International Conference on Electricity Distribution, Stockholm, Sweden.4 p.
@conference{69ba8d8600d746e5a263ab2d27e7113c,
title = "Demonstration of adaptive overcurrent protection using IEC 61850 communications",
abstract = "This paper contains a description of an adaptive protectionscheme that has been implemented and demonstrated in ahardware in the loop simulation environment using commercially available protection hardware and IEC61850 communications.The implementation is based on an actual 11kV system which includes distributed generation and network automation.IEC 61850 communications offers several benefits for the implementation of adaptive protection, but also presents some limitations which are discussed in the paper. An alternative approach to overcome a number of the limitations is also presented.",
keywords = "adaptive overcurrent protection, IEC 61850, communications",
author = "Federico Coffele and Blair, {Steven Macpherson} and Campbell Booth and John Kirkwood and Bob Fordyce",
year = "2013",
language = "English",
note = "CIRED 2013, 22nd International Conference on Electricity Distribution ; Conference date: 10-06-2013 Through 13-06-2013",

}

Coffele, F, Blair, SM, Booth, C, Kirkwood, J & Fordyce, B 2013, 'Demonstration of adaptive overcurrent protection using IEC 61850 communications' Paper presented at CIRED 2013, 22nd International Conference on Electricity Distribution, Stockholm, Sweden, 10/06/13 - 13/06/13, .

Demonstration of adaptive overcurrent protection using IEC 61850 communications. / Coffele, Federico; Blair, Steven Macpherson; Booth, Campbell; Kirkwood, John; Fordyce, Bob.

2013. Paper presented at CIRED 2013, 22nd International Conference on Electricity Distribution, Stockholm, Sweden.

Research output: Contribution to conferencePaper

TY - CONF

T1 - Demonstration of adaptive overcurrent protection using IEC 61850 communications

AU - Coffele, Federico

AU - Blair, Steven Macpherson

AU - Booth, Campbell

AU - Kirkwood, John

AU - Fordyce, Bob

PY - 2013

Y1 - 2013

N2 - This paper contains a description of an adaptive protectionscheme that has been implemented and demonstrated in ahardware in the loop simulation environment using commercially available protection hardware and IEC61850 communications.The implementation is based on an actual 11kV system which includes distributed generation and network automation.IEC 61850 communications offers several benefits for the implementation of adaptive protection, but also presents some limitations which are discussed in the paper. An alternative approach to overcome a number of the limitations is also presented.

AB - This paper contains a description of an adaptive protectionscheme that has been implemented and demonstrated in ahardware in the loop simulation environment using commercially available protection hardware and IEC61850 communications.The implementation is based on an actual 11kV system which includes distributed generation and network automation.IEC 61850 communications offers several benefits for the implementation of adaptive protection, but also presents some limitations which are discussed in the paper. An alternative approach to overcome a number of the limitations is also presented.

KW - adaptive overcurrent protection

KW - IEC 61850

KW - communications

M3 - Paper

ER -

Coffele F, Blair SM, Booth C, Kirkwood J, Fordyce B. Demonstration of adaptive overcurrent protection using IEC 61850 communications. 2013. Paper presented at CIRED 2013, 22nd International Conference on Electricity Distribution, Stockholm, Sweden.