This report details work carried out by the University of Strathclyde (UoS) to help SP Energy Networks (SPEN) with mass deployment of domestic PV systems on an already constrained distribution network. These installations were proposed by the Berwickshire Housing Association (BHA) and installed within the period February 2015 – January 2016. The key objective of the report is to provide an overview of the analysis used to investigate which proposed PV systems were able to be installed, and what effects they would have on the network. This report is produced as part of the Accelerating Renewable Connections (ARC) project for SPEN, which investigates alternative methods to allow integration of new DG connections onto a distribution network that previously was believed to be at full capacity.
LanguageEnglish
PublisherUniversity of Strathclyde
Commissioning bodySP Energy Networks
Number of pages114
Publication statusPublished - 15 Jun 2016

Fingerprint

Electric power distribution

Keywords

  • distributed generation
  • photovoltaic panels
  • energy networks

Cite this

Plecas, M., & Kockar, I. (2016). BHA PV scheme analysis. University of Strathclyde.
Plecas, Milana ; Kockar, Ivana. / BHA PV scheme analysis. University of Strathclyde, 2016. 114 p.
@book{e33940ea6da742c2a32cefddacf9ea3a,
title = "BHA PV scheme analysis",
abstract = "This report details work carried out by the University of Strathclyde (UoS) to help SP Energy Networks (SPEN) with mass deployment of domestic PV systems on an already constrained distribution network. These installations were proposed by the Berwickshire Housing Association (BHA) and installed within the period February 2015 – January 2016. The key objective of the report is to provide an overview of the analysis used to investigate which proposed PV systems were able to be installed, and what effects they would have on the network. This report is produced as part of the Accelerating Renewable Connections (ARC) project for SPEN, which investigates alternative methods to allow integration of new DG connections onto a distribution network that previously was believed to be at full capacity.",
keywords = "distributed generation, photovoltaic panels, energy networks",
author = "Milana Plecas and Ivana Kockar",
year = "2016",
month = "6",
day = "15",
language = "English",
publisher = "University of Strathclyde",

}

Plecas, M & Kockar, I 2016, BHA PV scheme analysis. University of Strathclyde.

BHA PV scheme analysis. / Plecas, Milana; Kockar, Ivana.

University of Strathclyde, 2016. 114 p.

Research output: Book/ReportCommissioned report

TY - BOOK

T1 - BHA PV scheme analysis

AU - Plecas, Milana

AU - Kockar, Ivana

PY - 2016/6/15

Y1 - 2016/6/15

N2 - This report details work carried out by the University of Strathclyde (UoS) to help SP Energy Networks (SPEN) with mass deployment of domestic PV systems on an already constrained distribution network. These installations were proposed by the Berwickshire Housing Association (BHA) and installed within the period February 2015 – January 2016. The key objective of the report is to provide an overview of the analysis used to investigate which proposed PV systems were able to be installed, and what effects they would have on the network. This report is produced as part of the Accelerating Renewable Connections (ARC) project for SPEN, which investigates alternative methods to allow integration of new DG connections onto a distribution network that previously was believed to be at full capacity.

AB - This report details work carried out by the University of Strathclyde (UoS) to help SP Energy Networks (SPEN) with mass deployment of domestic PV systems on an already constrained distribution network. These installations were proposed by the Berwickshire Housing Association (BHA) and installed within the period February 2015 – January 2016. The key objective of the report is to provide an overview of the analysis used to investigate which proposed PV systems were able to be installed, and what effects they would have on the network. This report is produced as part of the Accelerating Renewable Connections (ARC) project for SPEN, which investigates alternative methods to allow integration of new DG connections onto a distribution network that previously was believed to be at full capacity.

KW - distributed generation

KW - photovoltaic panels

KW - energy networks

UR - https://www.spenergynetworks.co.uk/pages/arc_accelerating_renewable_connections.aspx